Successful finish of first workover job with Coiled Tubing unit for «Gazprom Neft-Khantos» LLC.

Coiled tubing crew headed by the CT supervisor Mr. Atroshenko to pass technical audit in «GazpronNeft» LLC. The launch of mobile nitrogen membrane system.

Today, September 18, CT crew headed by the supervisor Mr. Atroshchenko has completed exponential well repair 14900 of Priobskoe oil deposit for «Gazpromneft-Khantos» LLC. The purpose of repair — «Normalizing / bottom-hole flushing to a depth of 3292 m, the elimination of asphalts, resins and paraffin in the tubing using coiled tubing».

The work started on the 16th of September 2010 at 22:00 am and terminated on the 18th of September 2010 at 14:00 pm. During the working process the mobile nitrogen membrane system was launched and tested. Thecomplex allows production of nitrogen from air in the working area.

Technical audit was successfully passed by the company. Below you can find the photo review.

The photo report (PDF, 12 Mb)